2010 Llama Tags   August 11, 2010 at 2:50pm

QC Teepad Party 8/14

Concrete is scheduled for Saturday 8/14 at 7:30am.

We are getting 10 yds with reinforcing fiber added. If we don't spill too much, we may be able to get 11 teepads done.

We will have 85 minutes to get the truck unloaded before they add an extra charges. We will fashion some type of plywood retaining lid for the skidsteer bucket to prevent as much spillage as we can. Paul will operate the loader and all other volunteers will quickly learn how to trowel concrete. While Paul is traveling back and forth in the loader, a few of the teepads could be done with wheelbarrow (#9 & #3 & #7)

Once the truck has offloaded and we've hosed down any tools, we should be able to start with the edging trowels. There will be extra trowels so we can stay on top of things.

We'd really like to see a dozen volunteers who can be there from 7:15 - Noon. That should be enough time to get the troweling done. Paul will stay and finish brooming if need be.